Official Document

User Acceptance Testing (UAT)

Car Wash Equipment Installation & Commissioning

Doc Ref: KUM-UAT-2026Version: v1.0Date: July 2026

Project Information

Project NameCar Wash Equipment Installation
Client / End UserTo be completed on site
Site LocationTo be completed on site
Equipment ModelTo be completed on site
Installation DateTo be completed on site
KU Machinery EngineerTo be completed on site
Document ReferenceKUM-UAT-2026
Revisionv1.0

Purpose & Scope

This User Acceptance Testing (UAT) document defines the criteria and procedures used to verify that the installed KU Machinery car wash equipment meets the agreed specifications and operates correctly before formal handover to the client.

The UAT covers mechanical installation, electrical connections, water supply, software/control system, wash cycle performance, safety systems, and operator training confirmation.

Successful completion of all test cases and sign-off by both parties constitutes formal acceptance of the installation.

Test Cases

1

Mechanical Installation

التركيب الميكانيكي

IDTest DescriptionAcceptance CriteriaResult / NotesStatus
TC-1.1Equipment frame is level and anchored to floor as per installation drawingsFrame level within ±2mm; all anchor bolts torqued to spec—Pending
TC-1.2All mechanical components (brushes, nozzles, gantry) installed and aligned correctlyNo visible misalignment; components move freely without obstruction—Pending
TC-1.3Water supply pipes connected and pressure-tested for leaksNo leaks at operating pressure (min. 4 bar); all joints sealed—Pending
TC-1.4Drainage system installed and flow verifiedWater drains freely; no pooling on floor during operation—Pending
2

Electrical & Control System

النظام الكهربائي ونظام التحكم

IDTest DescriptionAcceptance CriteriaResult / NotesStatus
TC-2.1Main power supply connected and voltage verified at control panelVoltage within ±5% of rated supply (380V / 220V as applicable)—Pending
TC-2.2Control panel powers on without fault codes or alarmsPanel displays normal startup screen; no error codes present—Pending
TC-2.3Emergency stop (E-Stop) buttons tested on all positionsMachine halts immediately on E-Stop activation; requires manual reset—Pending
TC-2.4All sensors (vehicle detection, limit switches, water level) functionalEach sensor triggers correct system response when activated—Pending
3

Wash Cycle Performance

أداء دورة الغسيل

IDTest DescriptionAcceptance CriteriaResult / NotesStatus
TC-3.1Pre-wash rinse cycle activates and covers full vehicle lengthWater coverage uniform; no dry spots on vehicle surface—Pending
TC-3.2Foam/chemical application system dispenses correct dosageChemical concentration within specified range; even foam coverage—Pending
TC-3.3High-pressure wash cycle operates at rated pressureOperating pressure ≥ specified rating (bar); nozzles unobstructed—Pending
TC-3.4Final rinse and drying cycle completes without residueVehicle exits with no soap residue; drying effective on standard test vehicle—Pending
TC-3.5Full wash cycle completes within specified timeCycle time within ±10% of specified duration—Pending
4

Safety Systems

أنظمة السلامة

IDTest DescriptionAcceptance CriteriaResult / NotesStatus
TC-4.1Safety light curtains / barriers prevent entry during operationMachine halts if barrier is breached during active wash cycle—Pending
TC-4.2Overload protection on all motors testedMotor protection trips within rated overload threshold; auto-reset disabled—Pending
TC-4.3Warning lights and audible alarm activate during machine operationAmber warning light and buzzer active throughout wash cycle—Pending
5

Operator Training

تدريب المشغل

IDTest DescriptionAcceptance CriteriaResult / NotesStatus
TC-5.1Operator training session conducted by KU Machinery engineerMinimum 4-hour hands-on training completed; attendance sheet signed—Pending
TC-5.2Operation manual and maintenance schedule handed over to clientPrinted and/or digital copies of all documents received by client—Pending
TC-5.3Client operator demonstrates ability to start, run, and stop machineOperator completes full wash cycle independently without assistance—Pending

Pre-Handover Acceptance Checklist

All test cases completed and results recorded
All test cases passed (or deviations formally noted and accepted)
Operation & Maintenance manual handed over
Spare parts kit (if included) handed over and inventoried
Warranty certificate issued
After-sales service contract discussed
Emergency contact details provided to client
Site left clean and free of installation debris

Deviations & Remarks

Any test cases that did not pass or items requiring follow-up action must be recorded below.

Ref.Description of DeviationAgreed ActionResponsible PartyTarget Date
—————
—————
—————

Sign-Off & Approval

By signing below, both parties confirm that the installation has been completed, all test cases have been reviewed, and the equipment is accepted for operational use.

Client / End User

Name

Title / Position

Company

Signature

Date

KU Machinery Representative

Name

Title / Position

Signature

Date

This document becomes legally binding upon signature by both parties. A copy shall be retained by each party.